In April 2009, the SWAI group was formed to discuss issues related to OpenFlow switch software architecture and implementation. The original webpage on the internal wiki was OpenFlow_SWAI.
Charter
TBD
Current Activities
- OpenFlow Hardware Abstraction API definition: Latest Draft from 9/16/09
- Testing Framework and Test Development
To do: Consider adding a table of current action items with entries for: Specific action, Current responsible party, Date created, Original/Current date due, Details (including dependencies), Log: if something (esp due date) changes, track reason here.
Meeting Notes
June 24, 2010
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Test framework and test development continued
- Asher's OpenFlow Porting Kit discussion
- Meeting Minutes
May 27, 2010
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Test framework and test development continued
- HAL update
- Meeting Minutes
May 13, 2010
- Gates 359, 10:00 AM - 11:00 AM (Need to verify room)
- Agenda:
- Openflowj demo
- Test framework and test development continued
- HAL update
- Netgear update
- Meeting Minutes
May 6, 2010
- Gates 359, 10:00 AM - 11:00 AM (Need to verify room)
- Agenda:
- Test framework and test development continued
- HAL update
- Openflowj: David's Java controller update (maybe)
- Meeting Minutes
April 15, 2010
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Test framework and test development continued
- Openflowj: David's Java controller
- NetFPGA update
- HAL update
- FP Churn issue update
- Reschedule next week's meeting
- Netgear interest
- Open vSwitch: How to engage?
- Meeting Minutes
April 9, 2010
- Gates 200, 11:00 AM - 11:30 AM
- Meeting Minutes
March 25, 2010
- Gates 260, 10:00 AM - 11:00 AM
- Agenda:
- Testing Framework discussion: See Testing Wiki Page
- Making test writing happen
- StressNet: We need a better test bed for OpenFlow switches/controllers
- Requirements (Find crashes, rough performance eval)
- Solutions (Resources, effort)
- Stanford OpenFlow system release targets
- Status of OpenFlow NetFPGA implementation
- Testing Framework discussion: See Testing Wiki Page
January 28, 2010
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Testing Framework discussion: See Testing Wiki Page
January 21, 2010
- No Meeting
January 14, 2010
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Follow-up on action items from last week's minutes
- Testing Framework discussion: See Testing Wiki Page
January 7, 2010
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Follow-up on action items from last week's minutes
- 1.0 compliant hardware availability plan
- Testing Framework discussion
- Plan for Bob's "Mininet"
December 17, 2009
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Follow-up on action items from last week's minutes
- Resolve queue error code issue
- Buttoning up 1.0 release
- Testing Framework discussion
December 10, 2009
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Follow-up on action items from last week's minutes
- 1.0 release status
- Testing Framework status
December 3, 2009
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Follow-up on action items from last week's minutes
- TBD
November 19, 2009
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Follow-up on action items from last week's minutes (at the bottom)
- TBD
November 12, 2009
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Follow-up on action items
- Have some slicing test results showing sliced traffic distribution (Yiannis)
- Define slicing testing within the production deployment (Yiannis to organize)
- Scope changes to reference implementation for IP in ARP (Bob L): Done Dave E implemented (with minor tweaks from Glen)
- Begin/organize review of test framework (David, Guido)
- Need a tee shirt design for OpenFlow 1.0 release. (Glen, Guido, David E)
- Follow-up on action items
November 5, 2009
- Gates 359, 10:00 AM - 11:00 AM
- Agenda:
- Follow-up on action items
- Review "User Space Queues" for reference implementation of slicing (Dan, Yiannis): Done; details in minutes
- (Still) Need updated NOX ETA (Guido from Nicira): Done 11/13 current plan. See emails on line from Martin/Nicira.
- Send out email to list indicating decision to decouple kernel space implementation from reference release. (Glen): Done; no major objections at this time.
- Attempt implementation of structure/object endian swapper (ntoh/hton) in Python; evaluate in SWIG context. (Guido, Tatsuya): Resolved: See minutes.
- Verify if queue support is on the requirements list for XE NetFPGA product (Dan). Done: Not currently in rqmts. See minutes.
- Forward pointer to initial test framework checkins (Tatsuya) Done on 10/29.
- Check with Brandon for a date for other spec changes that are on the 1.0 "to do" page (Glen) Done; current plan is 11/10.
- Follow-up on action items
Meeting Archive